Thursday, April 30, 2009
18 Main Is Complete
Opening the Range
The chipping green was aerified on Wednesday and will be open for putting, chipping and sand play. The putting green will be closed until further notice.
Tuesday, April 28, 2009
Beginning The Mainline
As far as the mainline install, LUI has begun with the 18th hole. It is a 6" line that dead ends at the green. Their goal is to get into a rhythm and the process should go pretty smooth. Jose Acosta is the Irrigation Superintendent and has got a great team of guys of to a positive start. The first step is to remove the sod, roll it up to be replaced later. Next the trench is dug carefully watching for the current irrigation to keep it together. They will fix any damage to our PVC system. While removing the soil, they use a small "triangle-shaped" screen to achieve the best bedding of fill around the pipe. The back fill is as follows; 1/2 inch minus for bed of pipe, 12-18" of 2 inch minus fill and finally 3" minus for topsoil. Before back filling, a saddle will be fused onto the pipe for all of the lateral valves. Once the valves, prv's, drains and communication are installed, back filling will commence, the sod replaced and a final clean up before moving on. Check out the picture bar in the morning for detailed photos of this process.
Green Light
The main reason for this work is to correct a life safety issue. Due to the severity of this, Vail Golf Club has no choice but to correct this issue ASAP. As you can see here the retaining wall is failing and the surface of the tee box is beginning to slide. The tee box is in poor health and does not set up properly with the green.
In this project all of the tee boxes will be re-shaped and expanded, most of the walls will be removed by a grass slope. The cart path will be re-aligned and trees, native grasses and even some wildflowers will be incorporated into the area. The timeline for this project is about 4 weeks. A temporary green for 2 and a tee for 3 will be in place until the new sod for the tee box rooted properly for play which could be mid-June.
There was a separate bid process for this work and Landscaped Unlimited won again. Along with the irrigation system, the goal is for both crews to work simultaneously to have the area prepared for irrigation so the new tee boxes can be established properly.
Sunday, April 26, 2009
Videos
Saturday, April 25, 2009
Re-visit New Orleans
Voles
Voles are rodents that look very similar to mice that wreak havoc to turfgrass in the wintertime. Every four to five years there is a spike in their population and they can create areas like this. 2009 is one of those highly populated years. These vegetarians can eat through turfgrass and perennial plants quickly and leave you with much less plant material in the spring than you had in the fall.
Over the past few years we have noticed most of these areas come back in time, but over seeding and getting proper nutrients to the damaged areas are a must. A few other observations we have noticed, first they fear fungicides and any areas that were applied with fungicides in the fall, keep away from through the winter. Also they stay away from the Nordic track and any other compacted areas. It is impossible for them to burrow through the ice layers.
Friday, April 24, 2009
What's Going On?
Tuesday, April 21, 2009
Three Tee Box Update
With temperatures in the 50's on Sunday and Monday some of this snow has melted away. Here, Tony is using the snowcat to move snow into sun exposed areas to encourage melting and speed up a construction start date. Demolition can begin at almost anytime, however there is still too much snow in this area to shape the soil. The dilemma is getting Landscapes Unlimited started in this area for a couple of days to demo, then only to stop and wait for further melting to continue. By the end of the week we should have a better idea with a construction schedule. All in all, we are looking at a 4-5 week process to have the 2nd green and third hole buttoned up.
Organizing
Monday, April 20, 2009
Cultural Practicies
Once the green is dry and growth begins we will incorporate sand topdressing and seed.
Saturday, April 18, 2009
Just Another Day
Friday, April 17, 2009
Great Scott
Scott O'Connell, (left) the VRD Building Maintenance Manager is meeting with another Scott from HP Geotech from Glenwood Springs, CO. They are in the excavated trench for the pump house and are discussing the soil profile and necessary fill requirements for the building. We have been given the "green light" to continue and our soils look great at that depth.
O'Connell has been making sure the building is installed properly, so I can focus on what is inside the building. Thanks for all your help.
The Foundation
Wednesday, April 15, 2009
Snowmold And More Snow
Moving In
Friday, April 10, 2009
Silt Fence
A Public Presentation
Wednesday, April 8, 2009
Free Golf
Getting it done
Tuesday, April 7, 2009
Back to Clearing Greens Again
Thursday, April 2, 2009
Our budget too
I read an article recently from Larry Alyward in Golfdom Magazine that spoke to golf maintenance budgets. He quoted John Miller, a veteran and certified Superintendent, who is also the LPGA Tour Agronomist. He summarized how a family dining experience can be quite similar to one's golfing experience. Miller said, "It's like the family that goes out to dinner four times a month. They won't go out to dinner four times a month in this economy. They might go out once or twice, and that once or twice better be a memorable experience for them wherever they go, or they will go someplace else."
Vail Golf Club is doing everything possible to provide the best golfing experience in 2009. We hope to see you here checking out our improvements.